Construction Measurement of Architectural and M&E Works

Question 1a

In-situ Finishes

SMM Clause 8.01 - In-situ Finishes

General Ceiling Areas: This refers to the total square m of the area in contact with base not including the opening(s) = 0.5m2

Beam Sides and Soffits: The measurements have different values in equals squares metres (m2), and specifies the values of the width.

Students looking for Best Assignment Help Australia can refer to this construction assignment sample to understand construction measurement principles, SMM standards, quantity take-off calculations and architectural work specifications

SMM Clause 8.02 - Width Classifications for Beams

Designation (Width) Beam sides and soffits:

  • Not exceeding 150mm wide
  • 150-300mm wide
  • 300-600mm wide
  • Exceeding 600mm wide
Figure 1: Beam Overlapping
(Source: Self-created in Auto CAD)

Measurement Example - In-situ Finishes

General Ceiling Area: Total area = 10.0m x 6.0m = 60.0m2

Suspend beam area (beam suspended, beam is not an opening) no deduction beam areas.

Beam sides, soffits (must be broader than 300 mm)

  • Beam B1 soffit: 10.0 m × 0.3 m = 3.0 m²
  • Beam B1 sides: (10.0 m × 0.25 m) × 2 = 5.0 m²
  • Beam B2 soffit: 10.0 m × 0.3 m = 3.0m²
  • Beam B2 sides: (10.0 m × 0.25 m) × 2 = 5.0 m²
  • Beam B3 soffit: 5.0 m × 0.3 m = 1.5 m²
  • Beam B3 sides: (5.0 m × 0.25 m) × 2 = 2.5 m²

Total beam area = 20.0m²

(ii) Preformed Tile Finishes

SMM Clause 9.01 - Preformed Tile Finishes

General Ceiling Areas: in square metres (m2) to the covered area, including the tile cutting and fitting allowance.

Beam Sides and Soffits: One at a time (linear metres (m) or square metres (m2) of narrow sections, or of wider sections).

SMM Clause 9.02 - Tile Finish Classifications

Different measurements on the basis of application:

  • Linear measurement - For widths ≤ 300mm
  • Area measurement - For widths > 300mm
  • Additional items - Cutting, fitting, and waste allowances

Measurement Example - Preformed Tile Finishes

General Ceiling Area:

Total area = 10.0m × 6.0m = 60.0m² (including 5% cutting allowance = 63.0m²)

General Ceiling Area:

Completely cut area = 10.0 m x 6.0 m = 60.0m2 (5% cut off allowance = 63.0m2)

Beam Sides and Soffits:

  • Beam B1 soffit (300mm) - 10.0 m (linear metres)
  • Beam B1 sides (250mm) - 10.0m × 2 = 20.0 m (linear metres)
  • Similar for other beams

Linear measurement of beam = 70.0 m

Reasons for Different Measurement Approaches

AspectIn-situ FinishesPreformed Tile Finishes
General Ceiling Area (m²) - no deductions for beams Area (m²) + cutting allowance
Beam Soffits Area (m²) by width categories Linear (m) if ≤300mm, Area (m²) if >300mm
Beam Sides Area (m²) by width categories Linear (m) if ≤300mm, Area (m²) if >300mm
Waste Allowance Minimal - included in rate Explicit cutting and fitting allowance
SMM Clauses 8.01, 8.02 9.01, 9.02

Question 1b

SMM Clause 11.02f - Timber Plates

Timber plates (wall plates, sole plates, head plates) measured in linear metres (m) with joint allowances for:

  • Lap joints: 10% allowance for overlaps
  • Scarf joints: 5% allowance for end connections
  • Corner connections: Additional length for corner laps

SMM Clause 11.02g - Bearing Timber

Bearing timber (joists, rafters, beams) measured in linear metres (m) with joint allowances for:

  • Scarfed joints: 5% allowance for lengthening joints
  • Housing joints: No additional allowance (included in bearing length)
  • Notching and cutting: Measured separately

Joint Types & Applications

Lap Joint (Timber Plates)

Figure 2: Lap Joint
(Source: Self-created in Auto CAD)

Usage: Wall plates, sole plates at corners and extensions

Reason for 10%: Requires significant overlap (typically 600-1000mm) for structural integrity

Scarf Joint (Timber Plates)

Figure 3: Scraf Cut
(Source: Self-created in Auto CAD)

Usage: End-to-end joining of plates in straight runs

Reason for 5%: Minimal waste in cutting and fitting scarf angles

Scarfed Joint (Bearing Timber)

Figure 4: Scraf Joint
(Source: Self-created in Auto CAD)

Usage: Extending the length of joists, rafters, and beams

Reason for 5%: Standard cutting allowance for end preparation

Practical Examples

Example 1: Wall Plate System

Building perimeter: 20m × 12m rectangular building

Available timber lengths: 6m standard lengths

Calculation:

  • Total perimeter = (20 + 12) × 2 = 64m
  • Lap joints at 4 corners = 10% allowance required
  • Scarf joints in long runs = 5% allowance required
  • Wall plate quantity = 64 x 1.10 = 70.4 m

Joint Analysis:

  • 20m sides: 4 pieces of 6m = 24m (need 2 scarf joints)
  • 12m sides: 2 pieces of 6m = 12m (need 1 scarf joint)
  • 4 corner lap joints require additional material

Example 2: Floor Joists (Bearing Timber)

Joist span: 8m clear span

Length of timber available: 6m standard length.

Joist spacing: 25 joists with a centre spacing of 400mm.

Calculation:

  • Length required per joist = 8.2m (including bearing).
  • Required scarfed extension 6m + 2.5m pieces.
  • Scarf joint allowance = 5%
  • Joint Quantity = 25 x 8.2 x 1.05 = 214.7 m

Example 3: Mixed Joint System

Roof Structure: plate and rafters hip roof

All Plates (SMM 11.02f):

  • Perimeter plates: 60m X 1.10 = 66m (lap joints on corners)
  • Internal plates: 20m x 1.05 = 21m (scarf joints only)
  • Total plates: 87m

Rafters (SMM 11.02g):

  • Common rafters: 45 x 4.5m = 202.5m
  • Hip rafters: 26m (scarf to be scarfed): 4 x 6.5m.
  • Scarf allowance: (202.5 + 26) x 1.05 = 239.9m
  • Total rafters: 240m

Summary of Joint Allowances

Joint TypeTimber TypeSMM ClauseAllowanceReason
Lap Joint Plates 11.02f 10% Substantial overlap required
Scarf Joint Plates 11.02f 5% End cutting and fitting
Scarfed Joint Bearing Timber 11.02g 5% Length extension cutting
Housing Joint Bearing Timber 11.02g 0% Included in bearing length

Question 2

Project Specifications

Roof Dimensions 15,000mm × 6,500mm (Plan)
Roof Pitch 45 degrees
Tiles Hugenot HP 10 clay interlocking tiles
Timber All structural timber shall be keruing preserved
Rafter Spacing 600mm c/c
Batten Spacing 300mm c/c
Underlay Two layers bitumen felt, 12mm thick overall

Key Calculations

  • Length of rafter = 3250 / cos45° = 4599 mm ≈ 4.6 m
  • Rafter number = (15000 – 200)/600 + 1 = 26 rafters
  • Area of roof = 15 x 4.6 x 2 = 138 m2
  • Batten per slope = 4600/300 = 16

Part (a): Roof Coverings Including Associate Underlays

LengthWidthHeight / ThicknessDescription
15.0m 4.6m - Hugenot HP 10 clay interlocking roof tiles, fixed to timber battens with galvanized nails, tiles to protrude 75mm from fascia board over gutter, including 5% waste allowance (2 slopes × 69m² × 1.05)
15.0m - 275mm dia Ridge tiles, 275mm diameter half round, matching Hugenot HP 10 tiles, bedded in cement sand mortar (15,000mm ÷ 300mm spacing)
30.0m - - Special eave tiles, matching Hugenot HP 10, at eaves of roof (15m × 2 eaves)
18.4m - - Special verge tiles, matching Hugenot HP 10, at gable ends (4.6m × 2 slopes × 2 gables)
15.0m 50mm 30mm Timber battens, 50 × 30mm, keruing preserved, fixed @ 300mm c/c to rafters with galvanized nails (32 battens × 15m each)
15.0m 4.6m 12mm Underlay comprising two layers of bitumen felt, 12mm thick overall, including 10% lap allowance (138m² × 2 layers × 1.10)
15.0m 4.6m 50mm Roof insulation, 50mm thick fiberglass with double sided sisalation foil 450, including 5% waste (138m² × 1.05)
15.0m 4.6m - Fabric mesh 3325 laid on underside of roof covering to support insulation

Part (b): Structural Timber Members Including Wall Plates

LengthWidthHeight / ThicknessDescription
4.6m 75mm 200mm Common rafters, 75 × 200mm, keruing preserved timber, spaced @ 600mm c/c, including 5% joint allowance for scarfed joints (26 rafters × 4.6m × 1.05)
3.25m 75mm 175mm Ceiling joists, 75 × 175mm, keruing preserved timber, spaced to match rafters @ 600mm c/c, including 5% joint allowance for scarfed joints (26 joists × 3.25m × 1.05)
15.0m 75mm 300mm Ridge board, 75 × 300mm thick, keruing preserved timber, including 5% joint allowance for scarfed joints (15m × 1.05)
15.0m 75mm 150mm Wall plates, 75 × 150mm, keruing preserved timber, placed on eaves brick walls between gable walls, including 10% joint allowance for lap joints (2 plates × 15m × 1.10)

Part (c): Fascia, Barge, Soffit Boards and Timber Bearers

LengthWidthHeight / ThicknessDescription
15.0m 275mm 30mm Fascia board, 275 × 30mm thick hardboard, at eaves including 2% joint allowance for butt joints (2 eaves × 15m × 1.02)
4.6m 275mm 30mm Barge board, 275 × 30mm thick hardboard, at gable ends including 2% joint allowance for butt joints (2 gables × 4.6m × 1.02)
15.0m 300mm 20mm Eaves soffit boards, installed at eaves, including 5% waste allowance (15m × 0.3m × 2 eaves × 1.05)
4.6m 300mm 20mm Verge soffit boards, installed at gable verges, including 5% waste allowance (4.6m × 0.3m × 2 gables × 1.05)
300mm 50mm 50mm Vertical timber bearers, 50 × 50mm × 300mm long, keruing preserved, to support soffit boards at eaves @ 600mm c/c (15m × 2 eaves ÷ 0.6m spacing)
300mm 50mm 50mm Horizontal timber bearers, 50 × 50mm × 300mm long, keruing preserved, to support soffit boards at verges @ 600mm c/c (4.6m × 2 gables ÷ 0.6m spacing)
- - - Three coats of enamel paint to soffit boards, primer, undercoat and finishing coat (12.4m² total soffit area × 3 coats)
- - - Galvanized nails, screws, and fixings for fascia, barge and soffit board installation, complete with all necessary brackets and fixings
100mm - - 100mm half round gutter, complete with brackets, joints, and end caps (15m × 2 eaves)

Accurate measurement and quantity take-off are essential skills in construction projects. Students can also explore Quantity Surveying Assignment Help to understand measurement standards, material calculations and construction cost estimation

Question 3a

Differences

Metal Doors & FramesTimber Doors & Frames

SMM Clause 12.01 - Metal Doors

  • Measured as complete items (number)
  • Dimensions must be stated (width × height × thickness)
  • Door type and specifications included
  • Fire rating and security level specified

SMM Clause 11.01 - Timber Doors

  • Standard doors: area measurement (m2)
  • Special doors: item measurement (number)
  • Timber species and grade specified
  • Door construction type detailed

SMM Clause 12.02 - Metal Door Frames

  • Measured as complete frame sets (number)
  • Frame profile and gauge specified
  • Installation method included
  • Weather sealing and threshold details

SMM Clause 11.02 - Timber Door Frames

  • Frame sections: linear measurement (m)
  • Complete frames: item measurement (nr)
  • Joint types and connections specified
  • Preservative treatment requirements

SMM Clause 12.03 - Metal Door Hardware

  • Measured as complete sets (set)
  • Hardware grade and specifications
  • Integration with door system
  • Security and access control features

SMM Clause 11.03 - Timber Door Hardware

  • Individual items measured separately (number)
  • Hardware type and quality specified
  • Installation requirements detailed
  • Finish and protection requirements

Question 3b

Project Specifications

Door Type 45mm thick single leaf Hercules Tacam blast resistant steel door
Fire Rating 4H fire rated complying with SS 332:2007
Door Dimensions 900mm (W) × 2100mm (H) × 45mm (thick)
Frame Dimensions 1013mm (W) × 2196mm (H) × 150mm (deep)
Frame Material Galvanized steel jamb with integral fixing lugs
Hardware Proprietary Tacam multi-point lockset, heavy duty hinges, flush bolt, door handle

SMM Reference

  • SMM Clause 12.01: Metal doors measured as complete items (nr) with dimensions and specifications stated
  • SMM Clause 12.02: Metal door frames measured as complete frame sets (nr)
  • SMM Clause 12.03: Hardware measured as complete sets or individual items (nr)

Quantity Take-Off Table

ParticularsLengthWidthHeight / ThicknessDescription
METAL DOOR LEAF
Metal door leaf 900 mm 2100 mm 45 mm 45mm thick single leaf blast resistant steel door, Hercules Tacam or approved equivalent, 4H fire rated complying with SS 332:2007, complete with factory applied primer finish, size 900mm × 2100mm × 45mm thick
METAL DOOR FRAME
Metal door frame 1013 mm 2196 mm 150 mm Galvanized steel door frame complete set, hollow core construction as per specifications, size 1013mm × 2196mm × 150mm deep, including integral fixing lugs for precast concrete wall, weather seal rebates (45mm and 50mm depths), and factory galvanized finish
Threshold and sill 1 set 1 set 1 set Door frame threshold and sill assembly, galvanized steel construction, complete with drainage channels and weather sealing, sized to suit frame opening
DOOR HARDWARE
Lockset 1 set 1 set 1 set Proprietary Tacam multi-point lockset complete with cylinder, keeps, striking plates, and all necessary components for blast resistant door system, factory tested and certified
Hinges 3 sets 3 sets 3 sets Heavy duty steel hinges, Tacam approved, minimum 100mm × 75mm × 3mm thick, complete with stainless steel pins and bushes, suitable for blast resistant door application
Flush bolt 1 set 1 set 1 set Flush bolt system, heavy duty construction, complete with top and bottom shoot bolts, operating mechanism, and all fixing accessories
Door handle 1 set 1 set 1 set Door handle set, Tacam approved, heavy duty lever handle with back plate, complete with cylinder escutcheon, emergency release mechanism, and all fixing screws
SEALING AND WEATHERPROOFING
Weather sealing 1 set 1 set 1 set Weather sealing system complete, including perimeter seals for 45mm and 50mm rebates, threshold seal, and all necessary gaskets for blast resistant performance
Fire sealing 1 set 1 set 1 set Fire sealing system, intumescent strips and seals as required for 4H fire rating compliance, complete with smoke seals and all fixing accessories
INSTALLATION AND FIXING
Concrete wall fixing 1 set 1 set 1 set Concrete wall fixing system, including anchor bolts, chemical anchors, and all necessary fixings for securing frame to precast concrete wall structure, complete with load distribution plates
Installation and commissioning 1 set 1 set 1 set Installation, adjustment, and commissioning of complete door system, including testing of all functions, verification of blast resistance and fire rating compliance, and provision of test certificates
FINISHING AND PROTECTION
Final finishing 1 set 1 set 1 set Final finishing and protection of door system, including touch-up of any installation damage, application of final protective coatings, and cleaning of all surfaces

Reference List

Concerned About Completing Your Academic Project?
Connect with us for professional support and guidance.
  • Fatai, O.B., Ohis, A.C., Liphadzi, M., Stephen, R.M. and Bola, O.S., 2023. Assessment of lean guided construction project monitoring and evaluation practices: issues and challenges. In Proceedings of the 31st Annual Conference of the International Group for Lean Construction (IGLC31) (pp. 1127-1137).
  • Hariyanto, V.L., Daryono, R.W., Hidayat, N., Prayitno, S.H. and Nurtanto, M., 2022. A Framework for Measuring the Level of Achievement of Vocational Students Competency of Architectural Education. Journal of Technology and Science Education, 12(1), pp.157-171.
  • Jalil, A.B.A., Md Fazil, F.B., Hashim, M.A.S.B. and Nawi, N.B., 2023, August. Mechanical and Electrical Issues in Prefabricated Housing; Their Real Causes and Corrective Steps. In International Conference on Electrical, Control & Computer Engineering (pp. 247-261). Singapore: Springer Nature Singapore.
  • Sazali, M.S., Ariffin, H.L.T., Mohd, N.I., Bahrodin, M.B. and Yusoff, N.N.S.M., 2025, June. Occupational Safety and Health in Construction Industry (Management) 2017: Awareness among Construction Stakeholders. In IOP Conference Series: Earth and Environmental Science (Vol. 1509, No. 1, p. 012009). IOP Publishing.
  • Tengan, C. and Aigbavboa, C., 2021. Validating factors influencing monitoring and evaluation in the Ghanaian construction industry: a Delphi study approach. International Journal of Construction Management, 21(3), pp.223-234.
  • Tengan, C., Aigbavboa, C. and Thwala, W.D., 2021. Construction project monitoring and evaluation: An integrated approach. Routledge.